North York, Toronto · Fourplex and garden suite

Product
Fourplex and garden suite, 5 rental homes
Status
Design and permitting
Metrosuite's role
Developer, designer, builder and construction manager
Ownership
Third-party ownership entity, affiliated with Metrosuite
Delivery method
Factory-built modules
Years
2026–2027

A fourplex and garden suite on an established North York street, in zoning review as of September 2026. Utility locates, water service and the Phase I environmental and geotechnical investigation are complete.

Moore Park shares its design, engineering and procurement with the Drewry and Pleasant buildings, so the three run as one programme with one drawing set and one manufacturer schedule.

Milestones

Zoning submissionSummer 2026
Site investigationSeptember 2026
Building permitTo follow zoning

As of September 2026. Planned dates depend on manufacturer and municipal schedules and are updated as they change.